AIR SUPPLY TANK AND FITTINGS REPLACEMENT - CONTINUED
0146 00
INSTALLATION - CONTINUED
2.
Coat pipe threads of drain valve (20), tee (19), check valve (18), bushing (17), two tees (16), elbow (15), safety valve
(14), and five connectors (13) with pipe sealing compound.
3.
Install drain valve (20), tee (19), check valve (18), bushing (17), two tees (16), elbow (15), safety valve (14), and five
connectors (13) in air supply tank (2).
4.
Install air supply tank (2), four washers (12), screws (11), washers (10) and new lock nuts (9).
5.
Connect cable (8) and install new cotter pin (7).
6.
Install primary I air tank (4), four washers (6) and new lock nuts (5).
7.
Connect tube (3) to primary I air tank (4).
8.
Connect six tubes (1) to air supply tank (2).
9.
Perform air system PMCS leak test (WP 0021 00).
10.
Install rear platform (WP 0200 00).
END OF WORK PACKAGE