4. Install doghouse upper bracket as follows (see Figure 3-72):
a. Install original doghouse floor panel (retained from Doghouse Armor Installation Phase I,
Paragraph 3-10, Step 3) and secure with original four screws (1/4-20 X 0.750 Long Screws). Torque
screws to 6 lb-ft.
b. Install doghouse upper bracket (1) and secure with two bolts (2), flat washers (3), and lock washers (4).
Torque bolts to 7 lb-ft.
c. Install original bolts (retained from Doghouse Armor Installation Phase I, Paragraph 3-10) to finish
securing the original doghouse floor panel. Torque bolts to 7 lb-ft.
NOTE
The following step will require two technicians.
d. Install three bolts (5), six flat washers (6), and three locknuts (7). Torque locknuts to 35 lb-ft.
INSTALLATION 3-144