TM 9-2320-363-34-2
31. REMOVE BEARING (37) FROM GROUND SLEEVE BORE (38).
Use general cleaning methods to clean all parts (page 2-30).
1.
INSPECT ALL PARTS FOR WEAR OR DAMAGE.
2.
REPLACE CONVERTER BYPASS VALVE SPRING, LOCKUP SHIFT VALVE SPRING, AND MAIN
PRESSURE REGULATOR VALVE SPRING IF LOAD-HEIGHT SPECIFICATIONS LISTED IN
FOLLOWING TABLE ARE NOT MET.
Spring Load-Height Specifications
I
Spring
Length Without Load
Length Under Load
Load
Converter
2.65 in.
1.62 in.
21.0 -23.0 lb
Bypass Valve
(67.3 mm)
(41.2 mm)
(9.6-10.4 kg)
Lockup Shift Valve
3.22 in.
(81.8 mm)
1.8 in.
(45.7 mm)
22.0 -24.0 lb
(10.0-10.9 kg)
Main Pressure
3.94 in.
2.64 in.
82.0 -87.0 lb
Regulator Valve
(100.1 mm)
(67.1 mm)
(37.2 -39.4 kg)
Use general repair methods to repair damaged parts (page 2-33).
14-43