TM 9-2320-363-34-1
5.
REPEAT STEP 4 FOR FRONT END OF TWO EQUALIZING BEAMS (2) IN FORWARD-REAR AXLE
(9).
6.
TIGHTEN FOUR NUTS (8) TO 210-240 LB-FT (285-325 N.m).
7.
INSTALL FOUR SADDLE CAPS (10), EIGHT WASHERS (11), AND EIGHT NUTS (12) ON TWO
SPRING ASSEMBLIES (13). TIGHTEN NUTS TO 225-275 LB-FT (305-373 N.m).
NOTE
Steps 8 and 9 are for forward-rear axle.
8.
REPOSITION FLOOR JACK FROM STEP 5 OF REMOVAL AND INSTALL 2 SPIDER ASSEMBLIES
(14), 16 WASHERS (15), 16 SCREWS (16), 16 WASHERS (17), AND 16 NUTS (18) ON BOTH
SIDES OF FORWARD-REAR AXLE (9). TIGHTEN NUTS TO 150-175 LB-FT (203.4-237.3 N.m) IN
SEQUENCE SHOWN.
9.
INSTALL FOUR AIR HOSES (19) IN BRAKE CHAMBERS (20).
10. REPEAT STEPS 8 AND 9 FOR REAR AXLE (21).
NOTE
Follow-on Maintenance:
Install rear brakeshoe and linings (TM 9-2320-363-20).
9-27